- Splash Canyon Waterpark
- Planning Application PA08-0037
|
|
2
|
|
|
3
|
- Waterpark project initially
submitted: July 2006
- Planning Commission public hearing: October 2006 (approved)
- Project appealed to City Council
- City Council public hearing: November 2006 (approved)
- Project CEQA document challenged: December 2006
- Court decision against CEQA document: October 2007
|
|
4
|
|
|
5
|
- What is a Conditional Use Permit?
- Discretionary Permit
- Allows a specific use for a specific property
- Subject to special terms and conditions in addition to City Development
Code requirements
|
|
6
|
- * 50% (approximately 185
vehicles) will arrive between 9:30AM and 12:00PM
- * 35% more will arrive before 3:30 PM (approximately 130 cars)
- * 15% (approximately 55 vehicles) will arrive between 3:30PM and
8:00PM
|
|
7
|
- Hours of Operation: Memorial Day to Labor Day - 10:00AM to 8:00 PM
- Number of Employees: 15 full-time employees and 300 seasonal/part-time
employees
|
|
8
|
|
|
9
|
|
|
10
|
|
|
11
|
|
|
12
|
|
|
13
|
- In-depth studies and a Environmental Impact Report (EIR) will be
prepared.
- EIR will identify potential areas of concern such as traffic, noise,
aesthetics, and air quality.
|
|
14
|
- Notice of Preparation (NOP) for EIR released: February 29, 2008
- NOP public review and comment period: March 3 to April 2, 2008
- Anticipated Draft EIR release: June/July 2008
- Anticipated Draft EIR public review and comment period: June/July 2008
- Anticipated Planning Commission Public Hearing: August 2008
- Anticipated grading and construction: September- May 2009
- Anticipated Opening: May 2009
|
|