Harveston Community Meeting
  • Splash Canyon Waterpark
  • Planning Application PA08-0037
2
Location
3
Project History
  •  Waterpark project initially submitted: July 2006


  • Planning Commission public hearing: October 2006 (approved)


  • Project appealed to City Council


  • City Council public hearing: November 2006 (approved)


  • Project CEQA document challenged: December 2006


  • Court decision against CEQA document: October 2007



4
Service Commercial Permitted Uses



5
Service Commercial Permitted Uses
  • What is a Conditional Use Permit?


  • Discretionary Permit


  • Allows a specific use for a specific property


  • Subject to special terms and conditions in addition to City Development Code requirements






6
Circulation






  • * 50% (approximately 185       vehicles) will arrive between 9:30AM and 12:00PM


  • * 35% more will arrive before 3:30 PM (approximately 130 cars)


  • * 15% (approximately 55 vehicles) will arrive between 3:30PM and 8:00PM





7
Project details
  • Hours of Operation: Memorial Day to Labor Day - 10:00AM to 8:00 PM


  • Number of Employees: 15 full-time employees and 300 seasonal/part-time employees



8
Site Plan
9
Site Plan
10
Buffering/Landscaping
11
Elevations
12
Slides/Water Rides
13
Environmental Process

  • In-depth studies and a Environmental Impact Report (EIR) will be prepared.


  • EIR will identify potential areas of concern such as traffic, noise, aesthetics, and air quality.



14
Project Timeline
  • Notice of Preparation (NOP) for EIR released: February  29, 2008


  • NOP public review and comment period: March 3 to April 2, 2008


  • Anticipated Draft EIR release: June/July 2008


  • Anticipated Draft EIR public review and comment period: June/July 2008


  • Anticipated Planning Commission Public Hearing: August 2008


  • Anticipated grading and construction: September- May 2009


  • Anticipated Opening:  May 2009





15
Conclusion
  •  Questions


  • Comments


  • Suggestions